RESORT ROAD WORK INFORMATION
RISOUL 1850 ROAD WORK INFORMATION
Following the natural disaster of December 1, 2023, the Department installed a temporary bridge to access the station in record time.
This temporary bridge will be replaced by the creation of a spiked wall and the reconstruction of a roadbed, along with safety work above and below the road.
Work will begin on April 22 and be completed around August 15, 2025.
The projected work schedule provided to us by the Department, including traffic restrictions, is as follows:
→ April 22 to May 30, 2025: Site installation and preparatory work, possible alternate routes
→ June 2 to 6, 2025: Removal of the temporary bridge. Traffic is prohibited upstream and downstream of the station day and night. Detour via the old resort road. Traffic conditions (vehicle type, tonnage, etc.) will be defined later based on the condition of the old road.
→ June 7 to August 15, 2025: Creation of a nailed wall and reconstruction of the roadbed. Traffic restrictions with the implementation of an alternate route.
Thank you in advance for your understanding.
This temporary bridge will be replaced by the creation of a spiked wall and the reconstruction of a roadbed, along with safety work above and below the road.
Work will begin on April 22 and be completed around August 15, 2025.
The projected work schedule provided to us by the Department, including traffic restrictions, is as follows:
→ April 22 to May 30, 2025: Site installation and preparatory work, possible alternate routes
→ June 2 to 6, 2025: Removal of the temporary bridge. Traffic is prohibited upstream and downstream of the station day and night. Detour via the old resort road. Traffic conditions (vehicle type, tonnage, etc.) will be defined later based on the condition of the old road.
→ June 7 to August 15, 2025: Creation of a nailed wall and reconstruction of the roadbed. Traffic restrictions with the implementation of an alternate route.
Thank you in advance for your understanding.